Tunbridge Wells Junction Improvement Package and A26 Cycle Improvements
- Capital Investment - Kent & Medway, Less than £2m, LGF1
Approval Status
Fully Approved
Delivery Status
LGF Project Delivered
Project Completion Date
Spring 2019
Update on Project
At the Accountability Board meeting in September 2021 a change request was considered for the project. The Board agreed that the change request should not be implemented as there were significant outstanding risks to both delivery and realisation of benefits as the project did not meet all the conditions for spend beyond 30 September 2021. It was agreed that the remaining £623,389 LGF should be reallocated to alternative projects on the LGF project pipeline. Accountability Board Meeting Minutes 10 September 2021
The third phase of the project to link the cycle network from Birchwood Avenue through to the Tonbridge and Malling Borough Council boundary will now seek alternative funding.
Capital Programme delivery update
Take a look at our update on the delivery of the Local Growth Fund (LGF) and Growing Places Fund (GPF) capital programmes.
£579m of investment to East Sussex, Essex, Kent, Medway, Southend and Thurrock
In total the SELEP Growth Deal with Government has brought £579m of investment to East Sussex, Essex, Kent, Medway, Southend and Thurrock. Over the lifetime of the Growth Deal (2015-2021) we aim to deliver 78,000 jobs and 29,000 homes across the SELEP area, with the Deal set to attract a further £960m of investment into the South East over the six year period.
Find out more here
Phase 2 Business Case
Change Request - Business Case Addendum